The Critical Path for the Network Activities Shown Below Is

question 93

Multiple Choice

The critical path for the network activities shown below is ________ with duration ________. The critical path for the network activities shown below is ________ with duration ________.   A)  A-B-D; 10 B)  A-B-E; 11 C)  C-E; 14 D)  A-D-E; 13 E)  A-B-C-D-E; 22