The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I = 10, and J = 6.
(a) What task must be on the critical path, regardless of activity durations?
(b) What is the duration of path A-B-E-H-J?
(c) What is the critical path of this network?
(d) What is the length of the critical path?
(e) What is slack time at activity H?
(f) What is the Late Finish of activity H?
(g) If activity C was delayed by six time units, what would happen to the project duration?
Situational Awareness
The ability to understand and interpret environmental elements with regard to time or space, to project their future status, and to act accordingly.
Contingency Plans
Prepared strategies to be used in response to unforeseen events or emergencies, ensuring operational stability.
Neutralizer
Something that makes another thing ineffective or counterbalances its effects.
Leader Behavior
The actions and attitudes exhibited by those in leadership positions, influencing the morale, performance, and satisfaction of followers.
Q5: The number of sets required for strength
Q17: What is the key difference between weighted
Q18: What are some of the ethical issues
Q24: Rapidly developing products and moving them to
Q32: Identify five countries from which Boeing's 787
Q37: Many services maintain records of sales noting:<br>A)
Q47: Why are organizations changing from standardization to
Q96: Activity D on a CPM network has
Q99: The _ strategy uses subsidiaries, franchises, or
Q162: A good description of source inspection is