If a one-group pretest-posttest study uses subjects as their own controls, which is the study design?


Definitions:

Budgeted Cost

The estimated financial expenditure for a project, activity, or operation, typically set during the planning phase.

Planned Value

In project management, it represents the estimated monetary value of the work planned to be done on a project at a given point in time.

Budget At Completion

The total budgeted cost of a project at its completion, including all planned expenditures and liabilities.

Request For Proposal

A formal document issued by an organization inviting suppliers to submit proposals for supplying goods or services.