The PCIC Index Measures the Project Percent Complete in Relation

question 69

True/False

The PCIC index measures the project percent complete in relation to the actual resources used so far on the project.


Definitions:

Quantity Variances

Differences between the expected and actual quantities of materials or products used or produced, influencing cost and efficiency.