Consider the Following Work Breakdown Structure

question 31

Multiple Choice

Consider the following work breakdown structure:
Consider the following work breakdown structure:   What is the estimated expected (mean) time for activity E? A) 35 days B) 36 days C) 39 days D) 40 days E) 45 days
What is the estimated expected (mean) time for activity E?