Consider the Following Work Breakdown Structure

question 32

Multiple Choice

Consider the following work breakdown structure:
Consider the following work breakdown structure:   What is the estimated slack time for activity D? A) 0 day B) 30 days C) 40 days D) 50 days E) 100 days
What is the estimated slack time for activity D?