The PERT Network Provides a Project Manager with a Plan

question 172

True/False

The PERT network provides a project manager with a plan that puts all the activities of a project in the correct order that they must be accomplished, shows which activities can be accomplished simultaneously, and, also gives the manager a good estimate of how long each activity will take to complete.


Definitions:

Heuristics

Mental shortcuts or rules of thumb that simplify decision making by reducing complex problem solving to simpler judgment processes.

Unscrambling

The process of rearranging letters or elements to restore them to a coherent or original order.

Defensive Strategy

A plan or course of action designed to protect oneself or an organization from criticism, harm, or other adverse effects.

Algorithm

A specific set of instructions for solving a problem or accomplishing a task, often used in mathematics and computer science.

Related Questions