A Subcontractor Has Submitted Design Documentation on the Deliverable Due

question 330

Multiple Choice

A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule. Which of the following should the project manager do NEXT?