Consider the following Activity-On-Node (AON) project (activity completion times are in days) .
Use this information to answer the following questions. Consider the following Activity-On-Node (AON) project (activity completion times are in days) .    -Refer to the figure.How long will take to complete the project? A) 15 days B) 14 days C) 13 days D) 12 days E) 11 days
-Refer to the figure.How long will take to complete the project?