What term is used for the original group of participants studied to develop a new psychological test or assessment tool?


Definitions:

Early Start Date

The earliest date on which a task or project activity can begin, taking into account constraints and preceding activities.

Lag Time

The delay between tasks that have a dependency, where one task cannot start until a certain period after the previous task has finished.

Gantt Chart

A visual tool for project planning that displays activities against time, often used for tracking project schedules.

Total Float

The amount of time that a project task can be delayed without causing a delay to the project's overall completion date.