Which of the following associations is correct?


Definitions:

PERT

The Program Evaluation and Review Technique is a tool for managing projects that helps in the scheduling, organization, and coordination of various project tasks.

Critical Path

The sequence of stages determining the minimum time needed to complete a project, where any delay affects the project's finish date.

Variance

A statistical measure that represents the dispersion or spread of a set of numbers, indicating how far each number in the set is from the mean.