A Project Being Analyzed by PERT Has 60 Activities, 13

question 20

Multiple Choice

A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, the probability that the project will take 224 days or more to complete is