Given the Project Within the Table Below Calculate
A

question 17

Essay

Given the project within the table below calculate
a. The critical path
b. The minimum project duration
c. The amount of slack for each activity
 Activity  Duration  (hours)  Immediate  Predecessors A4 None B3 None C10 None D7 B,CE1DF1EG5 A, F\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Duration } \\\text { (hours) }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} \\\hline \mathrm{A} & 4 & \text { None } \\\hline \mathrm{B} & 3 & \text { None } \\\hline \mathrm{C} & 10 & \text { None } \\\hline \mathrm{D} & 7 & \mathrm{~B}, \mathrm{C} \\\hline \mathrm{E} & 1 & \mathrm{D} \\\hline \mathrm{F} & 1 & \mathrm{E} \\\hline \mathrm{G} & 5 & \mathrm{~A}, \mathrm{~F} \\\hline\end{array}


Definitions:

Managerial Problem Solving

The process by which managers identify, analyze, and resolve issues affecting the organization's performance.

Common Difficulty

A problem or challenge that is frequently encountered by multiple individuals or groups.

Satisfice

A decision-making strategy that aims for a satisfactory or adequate result, rather than the optimal solution.

Cost-benefit Relationship

An analysis or assessment that compares the costs and benefits of a decision, project, or action to determine its feasibility or worth.

Related Questions