Your company is making experimental turbochargers for a new design of high-powered farm tractors. The production schedule for these new components is contained in the table below.
The first turbocharger, a trial unit, took 900 hours to produce. Based on your experience with similar products, the learning factor is 85%. You have 20 employees, and each employee works 160 hours per month. How many hours will be required in each month?
In which month(s) will overtime be required to meet the production schedule?
Median
The middle value in a list of numbers, which divides the dataset into two halves.
Mode
The value that occurs most frequently in a given set of data.
Standard Deviation
A measure of the amount of variation or dispersion of a set of values; a low standard deviation indicates that the values tend to be close to the mean of the set.
Variability
Refers to the degree of difference or deviation from the mean within a set of data.
Q3: An activity on a PERT network has
Q26: A Cpk index of 1.00 equates to
Q30: How is source inspection related to employee
Q32: A small hair styling salon has several
Q41: A product was priced assuming an 80%
Q49: A drawing that shows the dimensions, tolerances,
Q51: The use of product development teams in
Q60: In the logarithmic approach to learning curve
Q64: The effects of OM policies over many
Q107: Benchmarking requires the comparison of your firm