A work cell is required to make 80 computerized diagnostic assemblies (for installation into hybrid automobiles) each day. The cell currently works an eight hour shift, of which seven hours is available for productive work. These assemblies require five operations, with times of 1.0, 0.8, 2.4, 2.5, and 1.4 minutes each. What is takt time for this cell?
How many workers will be needed?


Definitions:

Engineering

The applied science of energy and matter.

Energy

A physical quantity that represents the ability to perform work, which can exist in various forms such as mechanical, thermal, chemical, electrical, and nuclear.

Science of Human Behavior

The systematic study of human actions and reactions in a variety of environments and situations.

Psychology

The science of human behavior.