An Assembly Line Is Assigned as Follows

question 63

Essay

An assembly line is assigned as follows. Station A- task A, B, and C. Station B- task D. Station C- task E and F. The task times are 7, 3, 2, 9, 4, and 5 minutes respective to A, B, C, D, E, and F. (Assume that there is no precedence relationships between the tasks, ie they can be accomplished in any order)
A. Calculate the efficiency.
B. What would the assignment of tasks to stations be using shortest processing time (assuming the current maximum station time remains the cycle time)?

Comprehend the steps involved in the planning process and how they contribute to achieving organizational objectives.
Understand the relationship between planning and other management functions such as organizing, leading, and controlling.
Appreciate the impact of external factors such as time horizons on the planning process.
Recognize the importance of flexibility and adaptability in planning to address unforeseen challenges.

Definitions:

Net Worth

The total value of all assets a person or entity owns minus the total value of all its liabilities.

Medicaid

A government-sponsored insurance program in the United States providing health coverage to individuals and families with low income and resources.

Range

The difference between the highest and lowest values in a set of numbers.

Uninsured Senior Citizens

Individuals over a defined age, often 65 and above, who do not have medical insurance coverage.

Related Questions