You have read that in JIT and lean production the optimum lot size is one, with some exceptions for packaging and physical limitations. If a product currently has a lot size of 25, what must happen to setup time for the lot size to truly fall to one?
Data for this problem are D=100 units, S=$75 based on setup time of 50 minutes at $1.50 per minute, and H=$40 per unit per year.
Primary Motive
Fundamental drives or motivations that are biological in nature, such as hunger, thirst, or the need for sleep.
Ethology
The scientific study of animal behavior, often with a focus on behaviors that are instinctive or genetically programmed.
Natural Habitat
The original environment in which a plant, animal, or organism lives and grows best, without human intervention.
Instinct Concept
The inherent inclination of a living organism towards a particular complex behavior.
Q15: Franz Boas is the undisputed father of
Q30: What is the term for an expert
Q34: Given the realities of the contemporary world,
Q41: A system has three components in parallel
Q45: Which of the following statements regarding finite
Q50: Problems arise with contemporary means of communication,
Q67: Complete the table, find average lateness,
Q77: _ is a lot-sizing technique that generates
Q83: Which of the following is specifically characterized
Q88: Biological races have been scientifically discredited not