A Methods and Measurements Analyst Needs to Develop a Time

question 20

Multiple Choice

A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers perform this task five times, with the following results:  Observation 12345 Time(Seconds)  8476808476\begin{array} { | l | c | c | c | c | c | } \hline \text { Observation } & 1 & 2 & 3 & 4 & 5 \\\hline \text { Time(Seconds) } & 84 & 76 & 80 & 84 & 76 \\\hline\end{array}
What is the standard time for this task if the employee worked at a 25 percent faster pace than average and an allowance of 20 percent of job time is used?


Definitions:

Lake Erie

One of the five Great Lakes in North America, bordered by Ontario, Canada, and several U.S. states, known for its fisheries, recreation, and historical significance in trade and transportation.

Hudson River

A major river in New York State that flows from the Adirondack Mountains down to New York City, historically significant for trade and transportation.

Market Economy

An economic system where supply and demand from consumers drive the production and pricing of goods and services.

Industrial Revolution

A period of major industrialization from the late 18th to early 19th century that transformed primarily agrarian, rural societies in Europe and America into industrialized, urban ones.

Related Questions