Consider the Following Work Breakdown Structure

question 100

Multiple Choice

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)  time for project completion? A)  100 days B)  140 days C)  199 days D)  200 days E)  440 days
What is the estimated expected (mean) time for project completion?