Consider the Following Work Breakdown Structure

question 5

Multiple Choice

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity E? A)  0 weeks B)  3 weeks C)  9 weeks D)  11 weeks E)  12 weeks
What is the estimated slack time for activity E?