A manager who is choosing the first acceptable alternative that comes to his or her attention while solving a problem is making an optimizing decision.


Definitions:

Crashing

A project management technique used to reduce the time for task completion by increasing the allocation of resources, often leading to higher costs.

CPM Network

A project management tool that uses critical path method (CPM) principles to model the activities and events of a project in a graphical network.

Critical Path

A sequence of critical tasks in a project timeline that need timely completion to ensure the project ends on its scheduled date.

CPM Network

A project management tool that uses critical path method to model tasks and their dependencies in a project to determine the optimum project schedule.