Acme,Inc,Produces Widgets

question 69

Multiple Choice

Acme,Inc.,produces widgets.To manufacture a new type of widget,it took 100 hours for the first widget.Acme estimates it has a 95% learning rate.Using the logarithmic approach,calculate the time it will take to manufacture the 75th widget.