Figure 10-1 Excerpt from Internet Project Risk Register

question 30

Multiple Choice

  Figure 10-1 Excerpt from Internet Project Risk Register -Consider the excerpt of the Internet Project risk register presented in Figure 10-1.Which of the following risk events should receive the highest priority for the development of risk responses?​  A)  A - project requires new technology and support structure  B)  B - web infrastructure lacks sufficient transaction capacity  C)  C - IS resources are spread too thin  D)  D - The intranet site suffers a security breach Figure 10-1 Excerpt from Internet Project Risk Register
-Consider the excerpt of the Internet Project risk register presented in Figure 10-1.Which of the following risk events should receive the highest priority for the development of risk responses?​ 


Definitions:

Res Ipsa Loquitur

A legal principle that infers negligence from the very nature of an accident or injury, in the absence of direct evidence on how any defendant behaved.

Plaintiff

An individual or entity who initiates a lawsuit against another party in a court of law.

Jurisdiction

The official power to make legal decisions and judgments, often defined by geographic area or type of case.

Proving Their Case

The requirement for a party in a legal dispute to present sufficient evidence to support their claims or defense.

Related Questions