Match the Following Project Stages with the Associated Value of a Project

question 43

Short Answer

Match the following project stages with the associated value of a project audit.
A)Initiation
B)Baseline schedule
C)Implementation
D)Preliminary plan / schedule budget
1)Less useful,plan frozen,flexibility of team limited
2)More or less useful,depending on importance of project methodology to successful implementation
3)Very useful,particularly for setting measurement standards to ensure conformance with standards
4)Significant value if audit takes place early-prior to 25 percent completion of initial planning stage