You Have Collected the Data for a Time-Cost CPM Scheduling

question 16

Multiple Choice

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below.
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.At what day do we achieve the lowest total project cost (i.e. ,direct plus indirect costs) ?
You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project  direct costs  are given below. The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.At what day do we achieve the lowest total project cost (i.e. ,direct plus indirect costs) ?   A) 16 days B) 15 days C) 14 days D) 13 days E) 12 days


Definitions:

Memory Tasks

Activities or exercises designed to assess or improve an individual's ability to store, retain, and retrieve information.

Vitamin B-1

Also known as thiamine, a nutrient essential for glucose metabolism and the functioning of the nervous system.

Korsakoff's Syndrome

A chronic memory disorder typically caused by severe deficiency of thiamine (vitamin B1), often associated with chronic alcoholism.

Memory Problems

Issues or impairments in the ability to recall or retain information, impacting daily functioning and activities.

Related Questions