Simple Project Listing of Five Activities,their Predecessors,and Their Respective Time

question 17

Multiple Choice

simple project listing of five activities,their predecessors,and their respective time estimates are presented below:
simple project listing of five activities,their predecessors,and their respective time estimates are presented below:   Using the CPM,which activities have slack in this project? A) A B) B C) C D) D E) C and E
Using the CPM,which activities have slack in this project?


Definitions:

Height In Plane

The measurement of an object's elevation or altitude in relation to a base level, typically in the context of aviation or topography.

Moon Illusion

The moon illusion is an optical illusion where the moon appears larger when it is close to the horizon than when it is higher in the sky, despite having the same actual size.

Horizon

The line at which the earth's surface and the sky appear to meet, or metaphorically, the limit of a person's knowledge, experience, or interest.

Elliptical

Having an oval shape or relating to an ellipse; also used metaphorically to describe speech or writing that is obscure or lacks completeness.

Related Questions