You Have Collected the Data for a Time-Cost CPM Scheduling

question 56

Multiple Choice

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below.
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.If you crash this project by one day what is the total (i.e. ,direct and indirect) project cost?
You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project  direct costs  are given below. The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.If you crash this project by one day what is the total (i.e. ,direct and indirect) project cost?   A) $2,150 B) $2,300 C) $2,400 D) $2,450 E) $2,500


Definitions:

Vision

A forward-looking statement or idea about what an organization or individual aspires to achieve in the future, acting as a guide for decision-making and strategic planning.

Creativity

The use of imagination or original ideas to create something; inventiveness that can be applied in problem-solving or artistic endeavors.

Social Media Tool

A digital tool or platform used to create, share, or exchange information and ideas in virtual communities and networks.

Successful Companies

Businesses that achieve their goals, sustain growth, and demonstrate profitability over time.

Related Questions