You Have Collected the Data for a Time-Cost CPM Scheduling

question 16

Multiple Choice

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below.
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.At what day do we achieve the lowest total project cost (i.e. ,direct plus indirect costs) ?
You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project  direct costs  are given below. The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.At what day do we achieve the lowest total project cost (i.e. ,direct plus indirect costs) ?   A) 16 days B) 15 days C) 14 days D) 13 days E) 12 days


Definitions:

Forgone Interest

The potential interest earnings lost by choosing to invest capital in one option over an alternative that offers a higher return.

Short-Run Adjustment

The process by which businesses alter their production levels or inputs in response to short-term changes in market conditions.

Local Bakery

A place of business that specializes in producing and selling bread, cakes, and other baked goods to consumers within a specific area.

Plastics Industry

An economic sector involved in the production, distribution, and recycling of plastic materials and products.

Related Questions