The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
 Task  Time (sec)  Predecessor  A 45 B 50 A  C 20 A  D 55 A  E 15 D  F 65 D  G 25 E  H 35 B, C, F, G \begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 45 & \cdots \\\hline \text { B } & 50 & \text { A } \\\hline \text { C } & 20 & \text { A } \\\hline \text { D } & 55 & \text { A } \\\hline \text { E } & 15 & \text { D } \\\hline \text { F } & 65 & \text { D } \\\hline \text { G } & 25 & \text { E } \\\hline \text { H } & 35 & \text { B, C, F, G } \\\hline\end{array}
-Refer to the scenario above. The process design team realizes that the potential spike in demand for this device requires increased output. They elect to add a seventh worker to their production team at the first station. What is the net effect of adding this worker?


Definitions:

Currency Speculators

Investors who buy and sell foreign exchange with the aim of making a profit from changes in exchange rates, influencing currency values and economic conditions.

Spot Trade

A transaction for the immediate delivery of a currency, financial instrument, or commodity.

Business Days

Days of the week excluding weekends and public holidays when businesses and government offices are typically open.

Forward Trade

Agreement to exchange currency at some time in the future.

Related Questions