-Use the Network Diagram and Activity Lengths in the Nodes

question 34

Multiple Choice

  -Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. A) 8 B) 13 C) 14 D) 21
-Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.