What is the slack time for Activity D given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor A5B7C8 A D7 AE4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \mathrm { A } & 5 & - - \\\hline \mathrm {B} & 7 &- - \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \mathrm {~A} \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & 9 & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}


Definitions:

Quantity Discounts

Price reductions given to customers purchasing large volumes.

Inventory Turnover

A financial ratio indicating how often a company's inventory is sold and replaced over a specific period.

Average Sales Period

The average time it takes for a company to sell its inventory, indicating the efficiency of its sales and inventory management.

Inventory Turnover Ratio

A metric that indicates how often a company's inventory is sold and replaced over a period of time.

Related Questions