It Costs $75 Per Day for Each Day That a Construction

question 78

Multiple Choice

It costs $75 per day for each day that a construction crew is on site.The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.Use this information to determine the lowest cost for this project.All times given are in days.  Normal Minimum Crash Cost ActivityTimeTime ($/day)   Predecessor A106$70B63$40C22 B D42$60 C E64$80 A F85$90D,E\begin{array}{|l|l|l|l|l|} \hline&\text { Normal }&\text {Minimum}&\text { Crash Cost }\\ \text {Activity}&\text {Time}&\text {Time}&\text { (\$/day) }& \text { Predecessor }\\\hline \mathrm{A}& 10 & 6 & \$ 70 & -- \\ \hline\mathrm{ B} & 6 & 3 & \$ 40 & -- \\\hline\mathrm{C} & 2 & 2 & - & \text { B } \\\hline\mathrm{D} & 4 & 2 & \$ 60 & \text { C } \\\hline \mathrm{E} & 6 & 4 & \$ 80 & \text { A } \\\hline \mathrm{F} & 8 & 5 & \$ 90 & \mathrm{D}, \mathrm{ E }\\\hline \end{array}


Grasp the concepts and calculations related to earnings per share and dividend yield.
Understand the purposes of different types of financial analysis (e.g., leverage, profitability).
Recognize the importance and purpose of an audit.
Understand the calculation and interpretation of various financial ratios.

Definitions:

Related Questions