A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using a late start schedule.
 Activity  Duration (days)  Activity Cost  Predecessor K10140L864K,MM1296N6120MP14168LQ12144N\begin{array}{|l|l|l|l|}\hline \text { Activity } & \text { Duration (days) } & \text { Activity Cost } & \text { Predecessor } \\\hline\mathrm{K} & 10 & 140 & \\\hline\mathrm{L} & 8 & 64 & \mathrm{K}, \mathrm{M} \\\hline \mathrm{M} & 12 & 96 & \\\hline \mathrm{N} & 6 & 120 &\mathrm{M} \\\hline \mathrm{P} & 14 & 168 & \mathrm{L} \\\hline\mathrm{Q} & 12 & 144 & \mathrm{N} \\\hline \end{array}


Definitions:

Legal Problems

Issues or disputes that involve the interpretation and application of laws, potentially leading to legal action.

Companies

Business entities formed to engage in commercial, industrial, or professional activities, often to generate profit.

Friendly Notes

Informal written messages that convey warmth, personal interest, or kindness, often used to maintain or strengthen relationships.

Goodwill Messages

Communications intended to foster positive relationships, express thanks, or offer good wishes, often in a business context.

Related Questions