Examlex

Solved

Use the Information in the Table and Assume That a Worker

question 86

Multiple Choice

Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage?  Activity  Duration  Predecessor  A 5 days B4 days  A C5 days  A D6 days BE6 days C,DF6 days E\begin{array} { | l | l | l |} \hline \text { Activity } & \text { Duration } & \text { Predecessor } \\\hline \text { A } & 5 \text { days } & - \\\hline B & 4 \text { days } & \text { A } \\\hline C& 5 \text { days } & \text { A } \\\hline \mathrm { D } & 6 \text { days } & B \\\hline E & 6 \text { days } & C ,D \\\hline F & 6 \text { days } & E \\\hline\end{array}


Definitions:

Proposal Preparation

The process of creating a document that outlines a plan for a project, including objectives, methods, and budget, to persuade or inform its audience.

Information-Intensive

Describing a task, process, or industry that relies heavily on the processing and analysis of large volumes of information.

Insignificant Activity

An action or task that has little to no impact on the overall outcome or goal.

Initial Source

The original starting point or origin from which information or materials are derived.

Related Questions