Consider the Portion of a Project Depicted by This Graph

question 73

Multiple Choice

Consider the portion of a project depicted by this graph: Consider the portion of a project depicted by this graph:   What is the earliest finish time for activity 10-11 (far right hand side) , if the earliest start time of 8-10 (upper left hand side)  is 12, and the earliest start time of 9-10 (lower left hand side)  is 13? A) 22 B) 23 C) 24 D) 25 E) 26 What is the earliest finish time for activity 10-11 (far right hand side) , if the earliest start time of 8-10 (upper left hand side) is 12, and the earliest start time of 9-10 (lower left hand side) is 13?