Task X Is Expected to Take 3 Days to Complete

question 4

Multiple Choice

Task X is expected to take 3 days to complete.The maximum (latest) earliest finish date for any predecessors to task X is 10.Therefore, the earliest finish for task X is:


Definitions:

Discharged from Liability

The legal release of an individual or entity from any further responsibility for a debt or obligation.

Scientific Management

A management theory developed by Frederick Taylor, focusing on improving economic efficiency and labor productivity through systematic observation and measurement.

Deliberate Tasks

Activities consciously planned and executed to achieve a specific goal.

Overspecialized Work

work that is narrowly defined and requires a very specific set of skills or expertise, potentially leading to limitations in adaptability and opportunities.