Given the Following Information: Use a Gantt Chart to Schedule

question 24

Multiple Choice

Given the following information: Given the following information:   Use a Gantt chart to schedule the jobs in order 1,2,3 and assume that jobs cannot be split.What is the makespan? A)  12 B)  9 C)  14 D)  3 Use a Gantt chart to schedule the jobs in order 1,2,3 and assume that jobs cannot be split.What is the makespan?