Consider the Following Work Breakdown Structure What Is the Estimated Expected (Mean) Time for Project Completion

question 28

Multiple Choice

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B  A  C, D 445056 B  D 456075 C  E 424548 D  F 314049 E  F 273639 F  End 587082\begin{array}{l}\begin{array} { l c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B } & - & - & - \\\text { A } & \text { C, D } & 44 & 50 & 56 \\\text { B } & \text { D } & 45 & 60 & 75 \\\text { C } & \text { E } & 42 & 45 & 48 \\\text { D } & \text { F } & 31 & 40 & 49 \\\text { E } & \text { F } & 27 & 36 & 39 \\\text { F } & \text { End } & 58 & 70 & 82\end{array}\end{array} What is the estimated expected (mean) time for project completion?


Definitions:

Grand Narrative

A broad, overarching story or theory that attempts to explain large-scale historical events and movements as coherent, unified phenomena.

Postmodern Theory

A theoretical stance that critiques grand narratives, emphasizes the role of language and symbols in social construction, and advocates for pluralism.

Classical Theoretical Tradition

A foundation in sociology and social theory that includes contributions from key thinkers like Marx, Weber, and Durkheim, focusing on the analysis of society and social phenomena.

Classic Theorists

Thinkers who have made significant contributions to social theory, including but not limited to Marx, Weber, and Durkheim, whose ideas form the foundation of sociological study.

Related Questions