Examlex

Solved

Consider the Following Work Breakdown Structure What Is the Estimated Slack Time for Activity A?
A)

question 119

Multiple Choice

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B, C  A  D 385062 B  E 9099108 C  End 85100115 D  F 192531 E  End 91100115 F  End 626568\begin{array}{l}\begin{array} { c c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B, C } & - & - & - \\\text { A } & \text { D } & 38 & 50 & 62 \\\text { B } & \text { E } & 90 & 99 & 108 \\\text { C } & \text { End } & 85 & 100 & 115 \\\text { D } & \text { F } & 19 & 25 & 31 \\\text { E } & \text { End } & 91 & 100 & 115 \\\text { F } & \text { End } & 62 & 65 & 68\end{array}\end{array} What is the estimated slack time for activity A?


Definitions:

Bank Statement Adjustment

The process of modifying the balance shown on a bank statement to reflect transactions or corrections not yet recorded by the bank.

Company Books Adjustment

Modifications made to the accounting records of a company to correct errors or align them with actual financial activity.

Note Collected

The receipt of payment or the collection of a note receivable.

Bank Statement Adjustment

The process of reconciling the difference between a bank's record of an account's balance and the amount shown in the account holder's books.

Related Questions