question 133

Short Answer

Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:
 Process Time (Hours)  Job  Center A  Center B W45X66Y12Z52\begin{array} { c } \quad\quad\quad{ \text { Process Time (Hours) } } \\\begin{array} { l c c } \text { Job } & \text { Center A } & \text { Center B } \\\hline \mathrm { W } & 4 & 5 \\\mathrm { X } & 6 & 6 \\\mathrm { Y } & 1 & 2 \\\mathrm { Z } & 5 & 2\end{array}\end{array} What is the sequence which will minimize throughput time?


Definitions:

Temporary Project Team

A group of individuals assembled for a specific project or task with a defined timeframe, disbanding once the project is complete.

Conflict and Chaos

Situations or periods marked by disagreement, disarray, and lack of order, which can lead to stress and dysfunction.

Communication

The exchange of information, thoughts, or messages through speech, signals, writing, or behavior.

Norming Stage

A phase in group development where members resolve conflicts and develop closer relationships and cohesion.

Related Questions