Using the Cut-And-Try Method for Aggregate Operations Planning We Can

question 64

Short Answer

Using the cut-and-try method for aggregate operations planning we can determine the production requirement in units of product.If the beginning inventory is 400 units,the demand forecast is 900 units and the required safety stock is 10% of the demand forecast,what is the production requirement?


Definitions:

Direct Labor-Hours

Refers to the measurable amounts of work effort contributed directly by laborers on the manufacturing floor towards the production of goods.

Manufacturing Departments

Specialized subdivisions within a manufacturing facility where different stages of the production process are carried out.

Markup

A term used in accounting and finance to describe the difference between the cost of a good or service and its selling price.

Activity At Capacity

The level of operations where a company or a production process is utilizing all available resources without any waste.