A Company Must Perform a Maintenance Project Consisting of Seven

question 68

Multiple Choice

A company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below:  Immediate  Activity  Designation  Predecessor  Time in Days  Break down both machines  A  None 3 Clean machine 1  B  A 3 Clean machine 2  C  A 3 Re-set machine 1  D  B 4 Re-set machine 2  E  C 2 Re-calibrate both machines  F  D and E 1 Final test  G  F 1\begin{array} { | l | l | l | l | } \hline & & \text { Immediate } & \\\hline \text { Activity } & \text { Designation } & \text { Predecessor } & \text { Time in Days } \\\hline \text { Break down both machines } & \text { A } & \text { None } & 3 \\\hline \text { Clean machine 1 } & \text { B } & \text { A } & 3 \\\hline \text { Clean machine 2 } & \text { C } & \text { A } & 3 \\\hline \text { Re-set machine 1 } & \text { D } & \text { B } & 4 \\\hline \text { Re-set machine 2 } & \text { E } & \text { C } & 2 \\\hline \text { Re-calibrate both machines } & \text { F } & \text { D and E } & 1 \\\hline \text { Final test } & \text { G } & \text { F } & 1 \\\hline\end{array}
Using CPM,which activities have slack in this project?


Definitions:

Reference Checking

The process of contacting previous employers, colleagues, teachers, or other individuals to verify the background, capabilities, and qualifications of a job applicant.

Related Questions