Benathir Donathat,director of the Project Committee,has Received Approval from Management

question 13

Multiple Choice

Benathir Donathat,director of the project committee,has received approval from management for implementation of a new accounting information system.After putting out an RFP,the committee settled on a vendor that will deliver all hardware and software required on a lease basis.Their decision is to go with