A company is considering a rate change, either an increase or a decrease in production, where Xt = production in a time period; Rt = increase in production rate from Period t−1 to Period t; Dt = decrease in production rate from Period t−1 to Period t. Which of the following is correct?


Definitions:

Slack

The amount of time that a task in a project can be delayed without causing a delay to subsequent tasks or the project completion date.

Earliest Start

The soonest time at which a particular task, project, or activity can begin, taking into account resource availability and constraints.

Latest Start

The latest time a task or activity can begin without delaying the project's completion date.

PERT

Project Evaluation and Review Technique, a method used to analyze and represent the tasks involved in completing a given project.