John Morton, director of materials management for Computer Products Corporation (CPC) in San Jose, is reviewing next year's plans for the supply of a component that is purchased from Osiega Ltd., a company in Japan. The component is the PS100 power supply assembly that is used in many of CPC's products.CPC pays the supplier more than $7 million per year for these units, and John wonders if money could be saved by developing another supplier for this component or if CPC should gear up to manufacture the power supply assemblies in-house within one of CPC's own production plants.John's purchasing-analysis staff has developed the following estimates:
The purchasing-analysis group has learned that CPC will need about 550,000 of the PS100 units next year.
a.Which supply source provides the least cost for next year?
b.How many PS100 units would have to be bought next year for each of the sources to be the least-cost source?
Cognitive Heuristics
Mental shortcuts or rules of thumb that simplify decision-making processes, often leading to quick, yet sometimes inaccurate, judgments.
False Positives
Instances where a test incorrectly indicates the presence of a condition or attribute that is actually not present.
Biased Thinking
The inclination or predisposition towards a particular perspective, idea, or result, often leading to unfair judgment.
Security Personnel
Individuals employed to ensure the safety and security of people and property.
Q17: Ensuring that a hotel staff at the
Q41: In the context of the perspectives of
Q51: As output decreases for a constant level
Q59: Discuss the six key current challenges in
Q64: Identify a true statement about corporate strategy
Q66: Employee satisfaction and employee turnover are examples
Q79: Which of the following is a quality
Q84: Lean operating systems seek to apply the
Q85: Refer to Table 1. Using this data
Q105: Discuss the three basic quality control practices