Steve, an operations manager at Krypto InfoTech, must set up an assembly line to assemble a computer mouse. The precedent network given below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast (output rate) is 60 units per shift. He decides to use the longest/largest-task-time rule to assign tasks to workstations.
SHAPE \* MERGEFORMAT
 Steve, an operations manager at Krypto InfoTech, must set up an assembly line to assemble a computer mouse. The precedent network given below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast (output rate)  is 60 units per shift. He decides to use the longest/largest-task-time rule to assign tasks to workstations. SHAPE \* MERGEFORMAT      Worksheet for assembly-line balancing problem   \begin{array}{|c|c|c|c|} \hline \text { Workstation } & \text { Assigned Tasks } & \text { Total Time } & \text { Idle Time } \\ \hline \text { A } & & & \\ \hline \text { B } & & & \\ \hline \text { C } & & & \\ \hline \text { D } & & & \\ \hline \text { E } & & & \\ \hline \text { F } & & & \\ \hline \end{array}  Use the previous assembly-line balancing (ALB)  information to answer Questions . -The task assigned to the third workstation (called C)  using the longest/largest-task-rule is _____. A)  task 3 B)  task 4 C)  task 5 D)  task 6  Steve, an operations manager at Krypto InfoTech, must set up an assembly line to assemble a computer mouse. The precedent network given below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast (output rate)  is 60 units per shift. He decides to use the longest/largest-task-time rule to assign tasks to workstations. SHAPE \* MERGEFORMAT      Worksheet for assembly-line balancing problem   \begin{array}{|c|c|c|c|} \hline \text { Workstation } & \text { Assigned Tasks } & \text { Total Time } & \text { Idle Time } \\ \hline \text { A } & & & \\ \hline \text { B } & & & \\ \hline \text { C } & & & \\ \hline \text { D } & & & \\ \hline \text { E } & & & \\ \hline \text { F } & & & \\ \hline \end{array}  Use the previous assembly-line balancing (ALB)  information to answer Questions . -The task assigned to the third workstation (called C)  using the longest/largest-task-rule is _____. A)  task 3 B)  task 4 C)  task 5 D)  task 6 Worksheet for assembly-line balancing problem
 Workstation  Assigned Tasks  Total Time  Idle Time  A  B  C  D  E  F \begin{array}{|c|c|c|c|}\hline \text { Workstation } & \text { Assigned Tasks } & \text { Total Time } & \text { Idle Time } \\\hline \text { A } & & & \\\hline \text { B } & & & \\\hline \text { C } & & & \\\hline \text { D } & & & \\\hline \text { E } & & & \\\hline \text { F } & & & \\\hline\end{array} Use the previous assembly-line balancing (ALB) information to answer Questions .
-The task assigned to the third workstation (called C) using the longest/largest-task-rule is _____.


Definitions:

Support Department Costs

Expenses associated with departments that provide internal support or services to other departments within a company rather than directly contributing to profit generation.

Production Departments

Divisions within a manufacturing company responsible for different stages of production processes, focusing on specific tasks or products.

Plantwide Factory Overhead Rate

Plantwide Factory Overhead Rate is the single overhead rate calculated by dividing total factory overhead by the total base (such as direct labor hours or machine hours) used to allocate overhead costs to products.

Overhead Costs

Expenses related to running a business that cannot be linked directly to a specific product or service, such as rent, utilities, and management salaries.