Assembly-Line Balancing Problem-Table 1 below
The Florida Appliance Company is installing an assembly line to produce vacuum cleaners, and Patrick, as an operations manager, is responsible for balancing the line. The work elements to be performed are listed, along with their items and immediate predecessors.
 Work  Immediate  Element  Time (sec)  Predecessor (s)   A 60B40 A  C 30 B  D 20 B  E 40 B  F 60 C G70 D H50 F, G  I 20 E J60 H, I \begin{array}{|l|l|l|}\hline\text { Work } && \text { Immediate } \\ \text { Element } & \text { Time }(s e c) & \text { Predecessor (s) }\\\hline\text { A } & 60 & -- \\B & 40 & \text { A } \\\text { C } & 30 & \text { B } \\\text { D } & 20 & \text { B } \\\text { E } & 40 & \text { B } \\\text { F } & 60 & \text { C } \\G & 70 & \text { D } \\H & 50 & \text { F, G } \\\text { I } & 20 & \text { E } \\J & 60 & \text { H, I }\\\hline\end{array}
-Use the information in Table 1. The company is planning to operate 2 shifts per day, 8 hours per shift. If the desired output rate of the line is 480 units per day, what is the cycle time?


Definitions:

Bias

A tendency to lean in a certain direction, either in favor of or against a particular thing, person, or group, often in a way considered to be unfair.

Agenda

A planned list or outline of items to be discussed, actions to be taken, or points to be considered in a meeting or event.

Time-intensive

Requiring a significant amount of time to complete.

Cost Effectively

Achieving an intended outcome or maintaining quality while minimizing expenses, often applied in the context of budgeting and financial planning in various fields.

Related Questions