Steve, an Operations Manager at Krypto InfoTech, Must Set Up

question 40

Multiple Choice

Steve, an operations manager at Krypto InfoTech, must set up an assembly line to assemble a computer mouse. The precedent network given below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast (output rate) is 60 units per shift. He decides to use the longest/largest-task-time rule to assign tasks to workstations.
SHAPE \* MERGEFORMAT
 Steve, an operations manager at Krypto InfoTech, must set up an assembly line to assemble a computer mouse. The precedent network given below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast (output rate)  is 60 units per shift. He decides to use the longest/largest-task-time rule to assign tasks to workstations. SHAPE \* MERGEFORMAT      Worksheet for assembly-line balancing problem   \begin{array}{|c|c|c|c|} \hline \text { Workstation } & \text { Assigned Tasks } & \text { Total Time } & \text { Idle Time } \\ \hline \text { A } & & & \\ \hline \text { B } & & & \\ \hline \text { C } & & & \\ \hline \text { D } & & & \\ \hline \text { E } & & & \\ \hline \text { F } & & & \\ \hline \end{array}  Use the previous assembly-line balancing (ALB)  information to answer Questions . -The task assigned to the third workstation (called C)  using the longest/largest-task-rule is _____. A)  task 3 B)  task 4 C)  task 5 D)  task 6  Steve, an operations manager at Krypto InfoTech, must set up an assembly line to assemble a computer mouse. The precedent network given below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast (output rate)  is 60 units per shift. He decides to use the longest/largest-task-time rule to assign tasks to workstations. SHAPE \* MERGEFORMAT      Worksheet for assembly-line balancing problem   \begin{array}{|c|c|c|c|} \hline \text { Workstation } & \text { Assigned Tasks } & \text { Total Time } & \text { Idle Time } \\ \hline \text { A } & & & \\ \hline \text { B } & & & \\ \hline \text { C } & & & \\ \hline \text { D } & & & \\ \hline \text { E } & & & \\ \hline \text { F } & & & \\ \hline \end{array}  Use the previous assembly-line balancing (ALB)  information to answer Questions . -The task assigned to the third workstation (called C)  using the longest/largest-task-rule is _____. A)  task 3 B)  task 4 C)  task 5 D)  task 6 Worksheet for assembly-line balancing problem
 Workstation  Assigned Tasks  Total Time  Idle Time  A  B  C  D  E  F \begin{array}{|c|c|c|c|}\hline \text { Workstation } & \text { Assigned Tasks } & \text { Total Time } & \text { Idle Time } \\\hline \text { A } & & & \\\hline \text { B } & & & \\\hline \text { C } & & & \\\hline \text { D } & & & \\\hline \text { E } & & & \\\hline \text { F } & & & \\\hline\end{array} Use the previous assembly-line balancing (ALB) information to answer Questions .
-The task assigned to the third workstation (called C) using the longest/largest-task-rule is _____.


Definitions:

Stereotypes

Oversimplified and generalized beliefs about a group of people that often do not reflect reality.

Programmed Decisions

Decisions that are made following established guidelines or procedures, typically for routine and recurring situations.

Spotlight Questions

Expose a decision to public scrutiny and full transparency.

Public Scrutiny

The critical observation or examination by the general public, often focusing on actions, decisions, or performance.

Related Questions