A print shop has four jobs that have to be processed through their only five-color press. They usually use the first come, first served (FCFS) rule of scheduling jobs. However, the customers are waiting in the lobby for these jobs so the shop wants to minimize the average waiting time. They are going to use the shortest processing time rule to do so. Processing times for each job are as follows (assume this is the arrival order) : Job A, 30 minutes; Job B, 17 minutes; Job C, 12 minutes; and Job D, 39 minutes.
-Using the first come, first served (FCFS) rule to sequence these jobs, the average waiting (flow) time is _____.


Definitions:

NHL Team

A professional ice hockey team that is a member of the National Hockey League, consisting of teams from both Canada and the United States.

Average Attendance

The mean number of individuals present over a series of events or over a period of time, calculated by summing the total attendance and dividing by the number of events or time intervals.

Number of Games

A term generally referring to the total count of matches or contests played in a particular sport or competition.

Life Expectancy

The average number of years a person is expected to live, based on statistical analysis of various demographic factors.

Related Questions