Examlex

Solved

Consider the Project Network and Data Shown Below ADetermine the Critical Path and the Project Completion Time

question 108

Essay

Consider the project network and data shown below:  Consider the project network and data shown below:    \begin{array}{|c|c|c|c|c|c|c|} \hline\text { Activity } & \text { Slack } & \begin{array}{c} \text { Normal } \\ \text { Time } \end{array} & \begin{array}{c} \text { Crash } \\ \text { Time } \end{array} & \begin{array}{c} \text { Normal } \\ \text { Cost } \end{array} & \begin{array}{c} \text { Crash } \\ \text { Cost } \end{array} & \begin{array}{c} \text { Crash Cost } \\ \text { Per Week } \end{array} \\ \hline \text { A } & 0 & 7 & 4 & \$ 400 & \$ 750 & \\\hline \mathrm{B} & 1 & 12 & 9 & \$ 1,000 & \$ 2,200 & \\ \hline \mathrm{C} & 0 & 7 & 6 & \$ 800 & \$ 1,100 & \\ \hline \mathrm{D} & 0 & 6 & 5 & \$ 600 & \$ 1,000 & \\ \hline \mathrm{E} & 0 & 8 & 6 & \$ 1,200 & \$ 2,200 & \\ \hline \mathrm{F} & 9 & 3 & 2 & \$ 800 & \$ 1,000 & \\ \hline \mathrm{G} & 9 & 3 & 2 & \$ 500 & \$ 650 & \\ \hline \mathrm{H} & 0 & 4 & 3 & \$ 400 & \$ 600 & \\ \hline \mathrm{I} & 0 & 6 & 5 & \$ 900 & \$ 1,300 & \\ \hline \end{array}   a.Determine the critical path and the project completion time. b.Determine the crash cost per week for all activities c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?  Activity  Slack  Normal  Time  Crash  Time  Normal  Cost  Crash  Cost  Crash Cost  Per Week  A 074$400$750B1129$1,000$2,200C076$800$1,100D065$600$1,000E086$1,200$2,200F932$800$1,000G932$500$650H043$400$600I065$900$1,300\begin{array}{|c|c|c|c|c|c|c|}\hline\text { Activity } & \text { Slack } & \begin{array}{c}\text { Normal } \\\text { Time }\end{array} & \begin{array}{c}\text { Crash } \\\text { Time }\end{array} & \begin{array}{c}\text { Normal } \\\text { Cost }\end{array} & \begin{array}{c}\text { Crash } \\\text { Cost }\end{array} & \begin{array}{c}\text { Crash Cost } \\\text { Per Week }\end{array} \\\hline \text { A } & 0 & 7 & 4 & \$ 400 & \$ 750 & \\\hline \mathrm{B} & 1 & 12 & 9 & \$ 1,000 & \$ 2,200 & \\\hline \mathrm{C} & 0 & 7 & 6 & \$ 800 & \$ 1,100 & \\\hline \mathrm{D} & 0 & 6 & 5 & \$ 600 & \$ 1,000 & \\\hline \mathrm{E} & 0 & 8 & 6 & \$ 1,200 & \$ 2,200 & \\\hline \mathrm{F} & 9 & 3 & 2 & \$ 800 & \$ 1,000 & \\\hline \mathrm{G} & 9 & 3 & 2 & \$ 500 & \$ 650 & \\\hline \mathrm{H} & 0 & 4 & 3 & \$ 400 & \$ 600 & \\\hline \mathrm{I} & 0 & 6 & 5 & \$ 900 & \$ 1,300 & \\\hline\end{array}
a.Determine the critical path and the project completion time.
b.Determine the crash cost per week for all activities
c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?


Definitions:

Posttesting

The evaluation of an advertising campaign or marketing strategy after it has been implemented, to assess its effectiveness.

Pretests

Preliminary tests or assessments conducted to evaluate the effectiveness or performance of a product, campaign, or theory before its full-scale implementation.

Target Audience

A specific group of consumers identified as the intended recipient of a product or marketing message.

Limited-Service Agencies

Advertising agencies that offer specific services such as creative design or media buying, as opposed to a full range of marketing and advertising services.

Related Questions