Consider the Project Network and Data Shown Below ADetermine the Critical Path and the Project Completion Time

question 108

Essay

Consider the project network and data shown below:  Consider the project network and data shown below:    \begin{array}{|c|c|c|c|c|c|c|} \hline\text { Activity } & \text { Slack } & \begin{array}{c} \text { Normal } \\ \text { Time } \end{array} & \begin{array}{c} \text { Crash } \\ \text { Time } \end{array} & \begin{array}{c} \text { Normal } \\ \text { Cost } \end{array} & \begin{array}{c} \text { Crash } \\ \text { Cost } \end{array} & \begin{array}{c} \text { Crash Cost } \\ \text { Per Week } \end{array} \\ \hline \text { A } & 0 & 7 & 4 & \$ 400 & \$ 750 & \\\hline \mathrm{B} & 1 & 12 & 9 & \$ 1,000 & \$ 2,200 & \\ \hline \mathrm{C} & 0 & 7 & 6 & \$ 800 & \$ 1,100 & \\ \hline \mathrm{D} & 0 & 6 & 5 & \$ 600 & \$ 1,000 & \\ \hline \mathrm{E} & 0 & 8 & 6 & \$ 1,200 & \$ 2,200 & \\ \hline \mathrm{F} & 9 & 3 & 2 & \$ 800 & \$ 1,000 & \\ \hline \mathrm{G} & 9 & 3 & 2 & \$ 500 & \$ 650 & \\ \hline \mathrm{H} & 0 & 4 & 3 & \$ 400 & \$ 600 & \\ \hline \mathrm{I} & 0 & 6 & 5 & \$ 900 & \$ 1,300 & \\ \hline \end{array}   a.Determine the critical path and the project completion time. b.Determine the crash cost per week for all activities c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?  Activity  Slack  Normal  Time  Crash  Time  Normal  Cost  Crash  Cost  Crash Cost  Per Week  A 074$400$750B1129$1,000$2,200C076$800$1,100D065$600$1,000E086$1,200$2,200F932$800$1,000G932$500$650H043$400$600I065$900$1,300\begin{array}{|c|c|c|c|c|c|c|}\hline\text { Activity } & \text { Slack } & \begin{array}{c}\text { Normal } \\\text { Time }\end{array} & \begin{array}{c}\text { Crash } \\\text { Time }\end{array} & \begin{array}{c}\text { Normal } \\\text { Cost }\end{array} & \begin{array}{c}\text { Crash } \\\text { Cost }\end{array} & \begin{array}{c}\text { Crash Cost } \\\text { Per Week }\end{array} \\\hline \text { A } & 0 & 7 & 4 & \$ 400 & \$ 750 & \\\hline \mathrm{B} & 1 & 12 & 9 & \$ 1,000 & \$ 2,200 & \\\hline \mathrm{C} & 0 & 7 & 6 & \$ 800 & \$ 1,100 & \\\hline \mathrm{D} & 0 & 6 & 5 & \$ 600 & \$ 1,000 & \\\hline \mathrm{E} & 0 & 8 & 6 & \$ 1,200 & \$ 2,200 & \\\hline \mathrm{F} & 9 & 3 & 2 & \$ 800 & \$ 1,000 & \\\hline \mathrm{G} & 9 & 3 & 2 & \$ 500 & \$ 650 & \\\hline \mathrm{H} & 0 & 4 & 3 & \$ 400 & \$ 600 & \\\hline \mathrm{I} & 0 & 6 & 5 & \$ 900 & \$ 1,300 & \\\hline\end{array}
a.Determine the critical path and the project completion time.
b.Determine the crash cost per week for all activities
c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?


Definitions:

Proactive Influence Tactics

Strategic behaviors employed to shape or alter the future environment or circumstances in a manner that is advantageous.

Direct Influence Tactic

A strategy used to persuade or influence others through direct communication or actions.

Leader Power

The ability of a leader to influence others and command respect and authority.

Rewards

Benefits, both tangible and intangible, given to employees as recognition for their work and to motivate continued performance.

Related Questions